We are currently working on our first permanent building at the Mavuno Village site. This building will be used to host short term families and volunteers. A few of the challenges we have experienced during the building process include unfaithful workers, difficulty in getting tax exemption on building materials, and a delayed inspection by the district engineer. Praise God that the district engineer finally visited and gave a positive assessment enabling us to proceed with the building.

September 2, 2007

September 24, 2007

October 3, 2007

October 11, 2007

October 12 , 2007

October 15, 2007

October 25, 2007

November 2, 2007

December 15, 2007

March 25, 2008